SPIE installs shared 110 kV overhead line infrastructure for Freiburg's new Dietenbach district

Published on 15 October 2026

Freiburg, 15 October 2026 – SPIE, the independent European leader in multi-technical services in the areas of energy and communications, is realising a new 110 kV shared power line corridor on behalf of the City of Freiburg as part of the development of the future Dietenbach district. The rerouting and bundling of the previously separate overhead lines belonging to DB Energie and Netze BW to form a shared corridor represents a key element in the development of the new neighbourhood, which is currently one of the largest urban development projects in Germany.

Dans le cadre de ce projet, SPIE assure la conception et l’installation de 13 nouveaux pylônes et déplace les lignes à haute tension existantes hors de la zone destinée à accueillir le futur quartier. Une ligne d’alimentation électrique ferroviaire de DB Energie reliant Fribourg à Appenweier et deux lignes aériennes de 110 kV exploitées par Netze BW entre Eichstetten et Fribourg seront ainsi regroupées sur une même série de pylônes sur une distance de 2,4 kilomètres. 

Avant la finalisation du nouveau tracé, une installation provisoire sera mise en service. Les tronçons de lignes existants seront ensuite démontés et la nouvelle ligne commune réalisée. Une fois celle-ci opérationnelle, l’infrastructure provisoire sera à son tour retirée. Les travaux ont débuté en mars 2026 et devraient s’achever à la As part of this project, SPIE is planning and installing 13 new overhead line pylons and rerouting the existing high-voltage power lines away from the district construction site. For this reason, a DB Energie railway power supply line between Freiburg and Appenweier, as well as two 110 kV overhead lines operated by Netze BW between Eichstetten and Freiburg, will be routed together on a single set of pylons over a distance of 2.4 kilometres. Before the new corridor is finalised, a temporary system will first be brought into operation. The existing sections of power line infrastructure will then be dismantled and the shared power line erected. Once it has been put into operation, the temporary route will then be removed. Construction work began in March 2026 and is due for completion in mid-2027. By consolidating several power lines within a single route, the project reduces the impact on the townscape.

The work is being carried out under challenging conditions in an inner-city environment, in the immediate vicinity of roads and public transport routes. A detailed logistics plan, extensive temporary arrangements and coordinated cooperation with the City of Freiburg, DB Energie and Netze BW ensure that everything runs smoothly and efficiently.

“This project involves urban development, energy supply, railway power, transport, planning permission and environmental requirements within a confined space. This is precisely where our strength lies: in our ability to reliably implement complex infrastructure projects,” says Daniel Hofmann, Project Manager at SPIE Germany Switzerland Austria.

“Today, state-of-the-art energy infrastructure must do more than simply ensure a secure supply of electricity. It must facilitate urban development, make efficient use of existing land and intelligently reconcile differing requirements,” says Boris von Lübtow, Business Unit Manager Transmission Lines at SPIE Germany Switzerland Austria. “Drawing on our expertise in high-voltage overhead line installation, we deliver solutions that combine technical excellence with the requirements of local authorities, infrastructure operators and local residents.”

  1.  DB Energie: Deutsche Bahn subsidiary responsible for railway power supply infrastructure in Germany.
  2. Netze BW: Regional electricity distribution network operator serving the German state of Baden-Württemberg.

     